If you’ve driven by the G.H. Dawe Community Centre lately, you would have seen considerable progress on construction. It’s been all hands on deck during the eight-week shutdown, with interior renovations taking place within the aquatics area and child-minding spaces. We’ve added a new fully accessible change room in the aquatics space, with adjustable lift and table, and accessible washroom and shower. We also added life guard office space, a new first aid room and a bookable meeting room right off of the pool for your next special event. This has temporarily shifted the existing gym space to the corridor until the full project completion which will see an exciting new gym space on the 2nd floor with workout equipment, a running track and studio spaces. New duct work was installed, and we completed renovations to the childminding space with the addition of a new washroom.
Overall, we are getting close to being able to fully enclose the facility. Structural steel and precast elements on site are nearing completion and roofers are working on the roof tie-in’s as well as the new roofing over the facility. We have trades continuing rough-ins and slab preparations for the facility and ice surfaces. Block partition walls are being installed within the new spaces and work on the parking lot preparation has also happened.
Recently, program staff at the Dawe staff got their first glimpse of the new spaces they will soon bring to life. Needless to say, they are very excited!